Construction Update: Home #45
We’re excited to share a update on the progress of Home #45—and it’s a big one. A Major Milestone Reached The fourth green inspection sticker has been placed on the front window of Home #45, marking the completion of a key set of required inspections. These green stickers represent important checkpoints in the construction process, and reaching this stage is a significant step forward for the home. (Photo: Green inspection stickers on the front window) Insulation Complete With inspections approved, we were able to move right into the next phase. DeVos Insulation came on site and successfully blew in the insulation, helping bring the home one step closer to being energy-efficient, comfortable, and ready for interior finishes. (Photos: Insulation being blown into the home) What’s Next? The momentum continues as we look ahead to the following steps: Home energy rating Rough-in inspection